Joint Base Pearl Harbor-Hickam, Hawaii — Construction of a new Navy dry dock at Pearl Harbor has advanced beneath the waterline, where crews are driving steel piles into the harbor floor and placing underwater concrete to form the base of a facility intended to bolster submarine maintenance in the Pacific for years to come.
The multiyear military construction effort, designated P-209, will deliver Dry Dock 5, a modern waterfront complex where ships and submarines can be serviced in a drained chamber. P-209 is part of the Navy’s Shipyard Infrastructure Optimization Program, or SIOP. “SIOP is a comprehensive, long-term recapitalization effort that is delivering integrated investments in infrastructure and industrial plant equipment at the Navy’s four public shipyards, expanding shipyard capacity and optimizing shipyard configuration to meet the Navy’s nuclear-powered fleet maintenance requirements,” said Mark Edelson, program executive officer for Infrastructure and Expeditionary. “As part of SIOP’s long-term, programmatic approach, our effort in building the new Dry Dock 5 includes lessons learned from previous megaprojects, and it is informing our approach to future megaprojects. All of this is part of our dedication to increase shipyard capacity and capability at our naval shipyards,” Edelson said.
Pearl Harbor Naval Shipyard & Intermediate Maintenance Facility (PHNSY & IMF) will operate the new dry dock once complete and certified, while Officer in Charge of Construction Pearl Harbor Naval Shipyard (OICC PHNSY) manages the build. OICC PHNSY, an echelon IV command under Naval Facilities Engineering Systems Command (NAVFAC) Pacific, oversees construction after contracts are awarded, monitors contractor compliance, quality and safety, and coordinates activities among contractors, the shipyard and other government organizations.
“Dry Dock 5 will significantly upgrade our shipyard’s capabilities,” said Capt. Ryan McCrillis, PHNSY & IMF commander. “It replaces Dry Dock 3, which was built during World War II to accommodate vessels of that era. Because Dry Dock 3 is too shallow for newer, larger Virginia-class attack submarines, Dry Dock 5 will be the first dry dock built specifically for the latest nuclear submarines. It is designed to add another century of maintenance capability to PHNSY & IMF’s inventory, keeping the fleet combat-ready in the Pacific.”
To ready the site, teams dredged sediment, set up laydown and fabrication areas at Waipio Peninsula, and erected a temporary trestle to move workers, equipment and large components over the water. The contractor’s plan centers on a cofferdam built from large steel pipe piles and interlocking sheet piles, creating a reinforced temporary enclosure that can be pumped dry so permanent dry dock walls can be built below the harbor’s surface.
Crews prefabricated nine concrete floor units at Waipio Peninsula, transported them by water and precisely lowered them onto the harbor floor. Divers and concrete plant operators are placing concrete underwater to tie the floor units into the surrounding foundation.
Beyond the dock chamber, P-209 also includes utility systems, crane-rail foundations, pump stations, a water treatment system, an electrical substation and 10 supporting buildings to provide power, drainage, crane access and operating space.
The next major milestone is dewatering the cofferdam to create a dry work area. “The ongoing preparations for dewatering are the most important and dangerous part of the project,” said Capt. Chris Coggins, OICC PHNSY commanding officer. “Without completing this phase, workers will not be able to safely enter or build at a depth of 60 feet below the adjacent waterline.”
Once dewatered, the temporary enclosure must resist pressure from the surrounding harbor. “First, the perimeter cofferdam pile driving needs to be completed and inspected,” said Coggins. “This provides the bathtub and door to safely keep the water out.” Crews are driving perimeter piles in stages—welding sections as they go to reach required depths—and installing braces and struts to connect parallel walls inside the cofferdam. Workers are also constructing the pump well that will drain Dry Dock 5 during future maintenance and using tremie pipes to deliver concrete underwater, connecting the prefabricated floor units to the perimeter while the area remains flooded.
The project depends on coordinated support across the Navy and industry. “Just as we rely on the broader Navy enterprise for guidance and parts to maintain submarines, we rely on NAVFAC, SIOP and industry partners to deliver Dry Dock 5,” McCrillis said. “This unified effort will ensure we have the facility needed to keep the Pacific Fleet ‘Fit to Fight.’”
The daily construction workforce is projected to increase from about 350 to more than 1,000 as the next phase begins, driving demand for skilled labor, concrete and other locally supplied materials. “This type of megaproject requires continued collaboration and coordination among all team members,” Coggins said. “Teamwork with local unions and batch plant operators to prioritize supplies will be key to the project’s success.”
As construction progresses, PHNSY & IMF personnel are preparing to operate the facility, participating in design, testing and planning, and expanding workforce pathways. “Our shipyard personnel are not just waiting for Dry Dock 5 to be built; they are actively involved in the design, testing and planning for future operations, ensuring we can begin maintaining submarines when it is completed,” McCrillis said. “We have many pathways to become part of our shipyard ‘ohana. The most popular is our Apprenticeship Program, which opens each year to approximately 150 new employees who learn a trade while earning a degree.”
NAVFAC Pacific leaders underscored the regional mission behind the work. “The mission of NAVFAC Pacific is to deliver infrastructure that enables the Fleet and Joint Force to deter, fight, and win,” said Rear Adm. Omarr Tobias, NAVFAC Pacific commander. “We do that by employing construction, engineering, and contracting expertise across the Pacific theater.” He added, “We are the engineering support to the Fleet. From constructing piers and runways to ensuring clean water and power at bases, we make sure our warfighters have the infrastructure they need to succeed—wherever they’re called to serve.”
“The Pacific requires disciplined speed, theater-wide portfolio thinking, and a government and industry co-created delivery ecosystem, from the expeditionary edge to the Foundry. The job ahead is massive, but the stakes are high.” Tobias said. “Peace, deterrence, and stability across the Pacific depend directly on the speed, durability, and resilience of the infrastructure we put in place today, from austere airfields to our largest dry docks. Our work must deliver the right capability – ready when the Joint Force needs it.”